LADONIA — Staff have put in the ultimate beam for the 1.1 -mile SH 34 bridge throughout the North  Sulphur River and the long run Lake Ralph Corridor in southeastern Fannin County.

“In roughly 23 months the workforce has gone from grassland to this milestone of setting the ultimate beam,” mission supervisor Josh Pfingst with Flatiron Building mentioned after the beam was laid in late August.  “This spectacular milestone included 360 drilled shafts, 144 columns, 48 caps and 353 Tx-54 concrete girders. Most significantly, it was achieved safely and on schedule.“